The Top 20 Secure PLC Coding Practices. Part 4 - Leave operational logic in the PLC wherever feasible

HMIs provide some level of coding capabilities, originally aimed to help operators enhance visualisation and alarming, that some programmers have employed to create code that shoul

Eugen WypiorEugen Wypior

Published 5 min read

PLCsecure codingOT securityIEC 62443ICS
Contents
  1. **Leave as much operational logic e.g., totalising or integrating, as possible directly in the PLC. The HMI does not get enough updates to do this well. **
  2. Guidance
  3. Example
  4. Why?
  5. References
  6. What’s next?
  7. Do you require help with secure coding of your PLCs?
  8. If you have any questions or require help in securely coding your PLCs, please contact SEQRED. SEQRED specialises in providing bespoke OT and IoT cybersecurity solutions. Our services cover such areas as Critical Infrastructure Protection, Cloud Services Security or Audits, and Threat Intelligence. For a full list of our services visit our services page – https://seqred.pl/en/services/
  9. About this article

Part 4 of the Top 20 Secure PLC Coding Practices series, originally published by admeritia GmbH (Langenfeld, Germany). SEQRED reproduces the series under the open license granted by the copyright holder. Full specification: plc-security.com.

**Leave as much operational logic e.g., totalising or integrating, as possible directly in the PLC. The HMI does not get enough updates to do this well. **

Security Objective Target Group
Integrity of PLC Logic Product Supplier
Integration /
Maintenance Service Provider
Asset Owner

Guidance

HMIs provide some level of coding capabilities, originally aimed to help operators enhance visualisation and alarming, that some programmers have employed to create code that should rather stay in the PLC to remain complete and auditable.

Calculating values as close to the field as possible makes these calculations more accurate. The HMI does not get enough updates to do totalising / integrating well. Also, there is always latency between HMI and PLC. Further, when the code is in the PLC, and an HMI restarts, it can always receive totalisers/counts from a PLC.

In particular, HMI code to be avoided is anything related to security or safety functions such as interlocks, timers, holds or permissives.

For analysing process data values over time, a process data historian is the better choice than the HMI. Use queries in a process historian database to compare totalised values (over a period, over a batch, over a process cycle) with totals aggregated locally in PLC logic. Alert on a variance greater than that can be explained by differences in data granularity.

Example

  • Code to establish conditions to enable/disable buttons: Enable/disable actions should be controlled on PLC layer, otherwise, actions can be performed on the HMI (or through network) in PLC, although not meeting (intended) conditions.
  • Timers to allow actions to the operator (delay timer for consecutive motor starts, timer to consider valves closed/open or motor stopped) should not be put on the HMI layer but in the PLC governing such motor/valve.
  • Thresholds for alarms have to be part of PLC codes although displayed on HMIs.
  • Water tank with changing volume: The PLC which controls flow in and out of the tank can easily totalise volume (and cross-validate totals). The HMI could do this as well, but it would need to get the values from the PLC first. These values would need accurate time-stamps in order to get correct totals in case of latency or and might miss values if the HMI restarts.

Why?

Beneficial for …? Why?
Security 1. Allows consistency in verifying code changes. HMI coding has its change control apart from PLC, generally not with the same rigor (especially in construction and commissioning phases), not allowing system owners to have a complete view and even losing important considerations. HMI’s do not include “forced signals” or changed value lists as PLCs or SCADAs, so HMI level changes are more difficult to be detected, practically impossible to be part of an authorisation change management plan. 2. For an attacker, it is harder to manipulate totals distributed over many PLCs than to manipulate totals all calculated in the HMI. 3. If a portion of the enable/disable functions are not in the PLC, attackers might be able to manipulate the PLC and I/O without having to work the HMI portion as the proper information is already obfuscated on the operator screen.
**************Reliability ** 1. Calculations are more efficient and accurate if closer to the field. Also, totals and counts will still be available if HMI restarts (PLCs do not restart as often and usually store these values in non-volatile memory). 2. Different sources for inputs and interlocks may mean non expected failures. There can be different technologies for HMIs in a plant (SCADA layer, but also field controller panels) and changes in one of those will fail to be disseminated through the rest of layers, leading to inconsistences in visualisation and possible failures in operation.
**Maintenance ** Coding is easy to understand and transfer from PLC to PLC, not so much from HMIs to HMIs.

References

Standard / framework Mapping
**MITRE ATT &CK for ICS ** Tactic:TA010 - Impair Process Control Technique:T0836 - Modify Parameter
**ISA 62443-3-3 ** SR 3.6 : Deterministic Output
**ISA 62443-4-2 ** CR 3.6 : Deterministic Output

What’s next?

In the next article of The Top 20 Secure PLC Coding Practices series, you will find out about using PLC flags as integrity checks

Do you require help with secure coding of your PLCs?

If you have any questions or require help in securely coding your PLCs, please contact SEQRED. SEQRED specialises in providing bespoke OT and IoT cybersecurity solutions. Our services cover such areas as Critical Infrastructure Protection, Cloud Services Security or Audits, and Threat Intelligence. For a full list of our services visit our services page – https://seqred.pl/en/services/

About this article

This article is reproduced from the Top 20 Secure PLC Coding Practices project coordinated by Sarah Fluchs (admeritia GmbH) and Vivek Ponnada (Nozomi Networks), with support from ISA Global Cybersecurity Alliance and S4 Events.

The full copy of the document is available at plc-security.com.

License

Copyright (c) 2021 admeritia GmbH, Langenfeld/Rheinland, Germany.

Permission is hereby granted, free of charge, to any person obtaining a copy of “Top 20 Secure PLC Coding Practices” and associated documentation files, to deal in the work without restriction, including the rights to use, copy, modify, merge, publish, distribute, sublicense, and/or sell copies, subject to preserving this copyright notice.

The work is provided “as is”, without warranty of any kind. Full license at plc-security.com.

See also

  • SEQRED’s synthesis article: Top 20 Secure PLC Coding Practices - a condensed guide
  • Full series: browse all 21 parts under the secure coding tag

Need help in this area?

Our experts will help you assess the risk and plan next steps.

Talk to an expert

We'll discuss scope, methodology, and timeline.

Book a call